Wednesday, January 7, 2009

Construction Update

An ice storm caused work to stop for today. Here is how the house looked at the end of yesterday. Shortly after this picture was taken, the logs for the second story arrived. They will get these logs into place over the next week. Then, next Wednesday the roof trusses arrive and will be lifted into place with a crane. One week after that, the window order arrives, and all of the windows will be placed.

2 comments:

  1. Hurray for the second story delivery! And with the trusses it will start to look like a home! Very exciting. I think we're priming the walls today - we have targeted Valentines Day as our official move in date - I'm kind of bummed, I was hopeing for January 20th, well really Sept 1st, then Thanksgiving, then Christmas...

    ReplyDelete

If you'd like to leave a comment...I assure you I appreciate it! I read and answer comments by email whenever possible. Thanks for stopping by for a chat with me!!